Most suitable for Construction scheduling of small to medium size Projects with a duration up to one year,
as well as for educational purpose.
If you are using IE8 please make sure to enable Active scripting in Internet Options
Note: The above tool is designed to produce a construction schedule for small projects, with a maximum of ten activities.
How to use this simple tool?
The Tables below shows the data entered for the Example Construction Schedule.
| Project Title | Example |
| Project Start Date: | 09-Jun-2010 |
| Project Completion Date | 05-Dec-2010 |
| No. of Activities | 6 |
| Activities | |||
| Code | Description | Duration (days) | Predecessor Activities |
| 1 | Activity 1 | 60 | |
| 2 | Activity 2 | 30 | 1,3,6 |
| 3 | Activity 3 | 30 | 1 |
| 4 | Activity 4 | 60 | 6 |
| 5 | Activity 5 | 30 | 2 |
| 6 | Activity 6 | 30 | 1,3 |