Scheduling Techniques
The four scheduling techniques widely used in construction projects are:
each is briefed below with a focus on Q
Scheduling being a new technique increasingly being applied in construction
management.
Bar Charts are the easiest and most widely used form of scheduling in
construction management. Even with other scheduling techniques the eventual schedule is presented the form of a bar chart. A
typical Bar chart is a list of activities with the start, duration and finish of
each activity shown as a bar plotted to a time scale. The level of detail of the
activities depends on the intended use of the schedule.
The linked bar chart shows the links between an
activity and its preceding activities which have to be complete before this
activity can start.
The bar charts are also useful for calculating
the resources required for the project. To add the resources to each activity
and total them vertically is called a resource aggregation. Bar charts and
resource aggregation charts are useful for estimating the work content in terms
of man-hours and machine hours.
Practically network analysis offers little more
than a linked bar chart, though its protagonists claim, with some justification,
that the self contained steps of a network are more applicable to complex
operations than the bar chart, and that the greater rigor imposed by the logic
diagram produces more realistic models of the proposed work. The steps in
producing a network are:
- Listing of activities
- Producing a network showing the logical relationship between activities.
- Assessing the duration of each activity, producing a schedule, and determining the start and finish times of each activity and the available float
- Assessing the required resources.
There are now two popular forms of network analysis in construction management
practice, activity on the arrow and activity on the node, the latter now usually
called a precedence diagram. Each of these approaches offers virtually the same
facilities and it seems largely a matter of preference which is used.
The line of Balance is a planning technique for
repetitive work. The principles employed are taken from the planning and control
of manufacturing processes greatly modified by E. G. Trimple. The basis of the technique is to find the required resources
for each stage or operation so that the following stages are not interfered with
and the target output can be achieved. The line of balance technique has been
applied in construction work mainly to house building and to a lesser extent to
jetty work and in conjunction with networks to road works.
The Q Scheduling is a new
technique, though getting rapid popularity among contracting firms. It is the only
scheduling
technique that reveals a relation between the
sequence of doing a job and the cost to be incurred. The Q schedule is similar
to the Line of Balance with some modifications made by A. R. A. Z. A in
2004, to allow for a varying volume of repetitive activities at different segments or
locations of the construction project, thus the model
produced is closer to reality. The following example explains the technique.
Having a project site with three buildings A,
B, C with following quantities
| Activity | unit | Average daily output |
Building A | Building B | Building C |
| Excavation |
m3 | 20 | 60 |
20 | 40 |
| Foundations |
m3 | 15 | 30 |
15 | 15 |
| Backfilling |
m3 | 30 | 30 |
60 | 60 |
Note: Above quantities are
chosen for illustration purpose and may not reflect a practical construction
case.
There are six possible arrangements for doing
the job in respect of location sequence with the constraint of ensuring a continuous
flow of work for each activity so that no idle time for employed crews might be
encountered, and no allowance for more than one activity to
take place simultaneously at one location:
- A - B - C,
- A - C - B,
- B - A - C,
- B - C - A,
- C - A - B,
- C - B - A
| Alternative 1 gives a total
duration of 10 working days |
| C | |
| | |
2 | 1 | | 2 |
| B | | | |
1 | | 1 | 2 |
| |
| A | 3 | 2 |
1 | | | |
|
| Days |
1 | 2 |
3 | 4 |
5 | 6 |
7 | 8 |
9 | 10 |
|
| Alternative 2 gives a total duration of 10 working days |
| B |
| | |
| | 1 |
1 |
|
2 |
| C |
| |
|
2 |
1 |
2 |
|
|
| A |
3 |
2 |
1 | |
| | |
| Days |
1 | 2 |
3 | 4 |
5 | 6 |
7 | 8 |
9 | 10 |
|
| Alternative 3 gives a total duration of 9 working days |
| C |
| |
| |
2 |
1 |
2 | |
| A |
|
3 |
2 | 1 |
| |
|
| B |
1 |
|
| 1 |
2 | |
| | |
| Days |
1 | 2 |
3 | 4 |
5 | 6 |
7 | 8 |
9 | 10 |
|
| Alternative 4 gives a total duration of 10 working days |
| A |
| | |
3 |
2 |
| 1 |
| C |
| 2 |
| |
1 |
| 2 | |
| B |
1 |
| |
| 1 |
2 |
| |
|
| Days |
1 | 2 |
3 | 4 |
5 | 6 |
7 | 8 |
9 | 10 |
|
| Alternative 5 gives a total duration of 10 working days |
| B |
| |
| |
| 1 |
| 1 |
2 |
| A |
| |
3 |
2 |
1 |
| |
| C |
2 |
| |
1 |
2 |
| |
|
| Days |
1 | 2 |
3 | 4 |
5 | 6 |
7 | 8 |
9 | 10 |
|
| Alternative 6 gives a total duration of 10 working days |
| A |
| |
| 3 |
2 |
2 |
| B |
| |
1 |
| |
1 |
| 1 |
| |
| C |
2 |
| |
1 |
2 |
| |
|
| Days |
1 | 2 |
3 | 4 |
5 | 6 |
7 | 8 |
9 | 10 |
|
The example shows that alternative 3 can
produce a saving of 10% relative to other alternatives, either in output rates
if duration is kept same, or in total duration and
subsequently in overheads and supervision costs. Actually Q Scheduling
software picks up alternative 3 as the most economic sequence and considers
other alternatives as having additional cost of 11.11% proportional to the most
economic alternative.
However, with a construction project having four locations there would be twenty four possible alternatives, and for a five
location project there would be 120 alternatives. For a project with ten locations there
would be three million, six hundred twenty eight thousand, and eight hundred
alternatives to consider.
Q Scheduling software is currently limited to consider up 5 locations; i.e. 120 alternatives so that it can work on normal computers -
Pentium II and above. It can be used efficiently for small to medium projects. However,
for the time being large projects can use Q Scheduling first by integrating
segments together so that a maximum total of five segments is there, then
considering each segment as a separate construction project. Thus a twenty five
location project can be handled.