. Cost Control and Cost information systems

Cost Control is an obvious objective in Construction Management and Construction Scheduling. It should be recognized that no amount of paperwork achieves this construction cost control. The actual control is achieved through the ultimate decision of the manager that something should be done differently and the translation of that decision into practice. The paperwork provides guidance on what control actions should be taken and therefore it is rather a cost information system.
The elements of a cost control system are:

  • Observation
  • Comparison of observation with some desired standard
  • Corrective action to take if necessary.

A construction cost control system should enable a manager to observe current cost levels, compare them with a standard plan or norm, and institute corrective action to to keep cost within acceptable bounds.

Most construction cost control systems have an inordinately long response time. Even the best cost control system would provide information on what was happening last week or last month. Since, in construction projects some activities might finish in a week or a month, then nothing could be done if the performance of such activities was reported to overrun estimates of respective costs.

. Developments in Cost Control Systems

There are three developments in construction management which show promise of improving cost control system in the construction industry

1. Short term scheduling and control.

This system was developed at Loughborough University in association with a contractor. It aims to merger the planning and supervision and hence to obtain a more or less zero response time.

. 2. Project Cost model.

This a system developed by Dr Martin Barnes for simulating future actions and thus guiding the manager in his choice between them

. 3. Quantitative scheduling

One of the unique Construction Software that provides a futuristic construction cost control tool for construction management is the CFF3 for cash flow forecasting. Version three has taken into consideration the possible deviations from estimates of cost as well as cash in patterns and provided a means to return back to the original estimate by damping out these deviations through the remaining period of construction. Updated estimates are provided each time an actual figure is added such that the end cost remain same as was originally estimated. It provides an excellent guide for managers through the construction project to capture the best possible actions in each period activities. Labor rate and efficiency constitute the core of Quantitative Scheduling which is highly recommended if cost minimization in respect of productivity rates is sought.
Also Construction Cost is directly related to Material price, Material usage and waste, Fixed and varied overhead expenditure. These are the areas where managers should seek action for future adjustments in order to get back to original estimate or practically as near as possible.

Top of the page






. CM Reporter v2

In view of the current status of construction progress, when is the project likely to be completed? An efficient construction management reporting tool for reliable estimation of the time required for completion of construction works. CM reporter software is a unique tool for project managers and construction claim advisers.
Software Details

Copyright © 2007 misronet. 
[ Home ]  [ Software ]  [ e-books ]  [ Directory ]  [ Articles ]