Cost Control is an obvious objective in Construction Management and
Construction Scheduling. It should be recognized that no amount of paperwork achieves this
construction cost control. The actual control
is achieved through the ultimate decision of the manager that something should
be done differently and the translation of that decision into practice. The
paperwork provides guidance on what control actions should be taken and
therefore it is rather a cost information system.
The elements of a cost control system are:
- Observation
- Comparison of observation with some desired standard
- Corrective action to take if necessary.
A construction cost control system should enable a manager to observe current cost levels,
compare them with a standard plan or norm, and institute corrective action to to
keep cost within acceptable bounds.
Most construction cost control systems have an inordinately long response time. Even the
best cost control system would provide information on what was happening last
week or last month. Since, in construction projects some activities might finish
in a week or a month, then nothing could be done if the performance of such
activities was reported to overrun estimates of respective costs.
There are three developments in construction management which show promise of improving cost control
system in the construction industry
This system was developed at Loughborough University in association with a contractor. It aims to merger the
planning and supervision and hence to obtain a more or less zero response time.
This a system developed by Dr Martin Barnes for
simulating future actions and thus guiding the manager in his choice between
them
One of the unique
Construction
Software that provides a futuristic construction cost control tool for
construction management is the
CFF3
for cash flow forecasting. Version three has taken into consideration the
possible deviations from estimates of cost as well as cash in patterns and
provided a means to return back to the original estimate by damping out these
deviations through the remaining period of construction. Updated estimates are
provided each time an actual figure is added such that the end cost remain same
as was originally estimated. It provides an excellent guide for managers through
the construction project to capture the best possible actions in each period
activities. Labor rate and efficiency constitute the core of
Quantitative
Scheduling which is highly recommended if cost minimization in respect of
productivity rates is sought.
Also Construction Cost is directly related to Material price, Material usage
and waste, Fixed and varied overhead expenditure. These are the areas where
managers should seek action for future adjustments in order to get back to
original estimate or practically as near as possible.
Top of the page
In view of the current status of construction progress, when is the project likely to be completed? An efficient
construction management reporting tool for reliable estimation of the time required for completion of construction works.
CM reporter software is a unique tool for project managers and construction claim advisers.
Software Details