Construction Delay Estimating and Management Software
CM Reporter Software for Construction
management provides an overall preview of the project progress. A popular
construction management software, used each month by top mangers to check where
the project stands and when it is most likely to be finished.
This simple, yet efficient, construction
management software is aimed at providing an overall preview of the project
progress for top level management. Since each project will have its own
peculiarities, this software is to be an "Alarm" calling for further
investigations if required. The ease of use and rapidness and conciseness of
report production made this software a popular construction management software,
used each month by top mangers to check where the project stands and when it is
most likely to be completed.
The enhanced version provides graphical presentation of the progress
status in comparison to the ideal performance as well as predictions of the most
probable completion date of the works and estimation of the next payment to be
made in accordance with the statistically deduced relation between cost and
time, applicable to the majority of building works. Also helps assess the
responsibility of encountered delays. A worthwhile tool for construction claim
assessment.
The report to be presented using enhanced version is customizable to include
specific data of user (such as company name, project title, reporter name...etc)
as well as save project data option.
The empirical S-curve relation between Progress and Time, which would result in
from a proper construction scheduling is the core of analysis. Presented reports
by this unique construction management software include a focus on performance
as well as an estimate of the delay in progress.
Main Software features
Graphical presentation of actual and estimated progress status
Estimation of the most probable project completion date in view of the current progress status
Estimation of next scheduled payment to be made by the Employer
Assessing the responsibility for the delay with a unique analysis that helps in claim assessments
How CM Reporter determines responsibility for delay?
The technique adopted by CM reporter construction software is a periodical
exercise to monitor progress impediments and try to remove their effect and
catch up as early as possible. This is achieved by comparing current status of
progress as well as progress in the month before with scheduled progress of the
works. Each month an estimation of the end date is calculated based on the
S-Curve analysis, where the following possible cases would be checked, while
Case 1 is our focus for scrutinizing delay responsibility
Case 1: Estimated end date is later than
contractual end date (i.e. an overall delay in the project completion is
foreseen)
If the estimated end date is found to remain same as that estimated at the
end of month before, it is concluded that the Contractor activities are
going along an S-curve parallel to the one produced from original schedule
with a simple shift. It is then assumed that certain impediment force have
resulted in the shift of the progress curve (Likely to be an external
force)
If the estimated end date is found to have moved later than the date
estimated by the end of month before, it is concluded that the Contractor's
performance is slower than should be, and therefore the Contractor
himself is likely to be responsible for the delay unless specific causes are
explained by him to have been beyond his control.
If the end date is found to have moved earlier than the date estimated by
the end of the month before, it is concluded that Contractor has
accelerated his performance and is trying to catch up with schedule. It
also could be that he has already caught up with schedule which leads in
Case 2 or even more has became ahead of schedule which leads to case 3
Case 2: Estimated end date coincides with
contractual end date (No delay in the project completion is foreseen)
Case 3: Estimated end date is earlier than contractual end date (An early
completion of the works is foreseen)
By doing so CM Reporter construction software not
only considers the current construction progress situation but also the rate of
change of this situation which can be called a second degree analysis of
progress.
Windows 98/ME/2000/NT/XP, IE5.0 or later Cookies
enabled
Awards and certificates
Purchase CM Reporter Software
Price: $26.7 However, you can take
advantage of the discount offer valid till:
(beyond which price may increase) and get the Enhanced Reporter for only $
19.95, that is 25% off List Price.